23 November, 2007 / TargetProcess v.2.7 Progress. Iteration #12.3 Completed

0 comments

Today we've completed third iteration of v.2.7. Report engine implementation going really well and right now it is possible to extract list of entities with

  • defined columns (including related entities columns)
  • set columns order
  • defined filters (including related entities filters)

For example, you may extract all user stories with all columns like Name, Effort, Iteration Name, Feature Name where User Story Effort = 0 and User Story Feature Priority is Must Have.

It is required to add calculations to the reports engine as well as more flexible columns. In final release it will be possible to create let's say a report like that

ID

User Story Name

Test Cases Passed

Test Cases Failed

Total Test Cases

Open Bugs

12

Workflow per project

8

4

12

5

33

Custom field type (numeric)

4

0

4

0

45

Average column

3

0

3

2

Development of Program Releases Management is in progress as well. In this iteration we've added product backlog to release plan with sorting and filtering options. There are some things to do in next iteration like drag and drop planning, release date forecasting and some smaller things.

Also we've integrated Selenium tests with Cruise Control and at least we have good build process setup :)

Labels: , , , ,



20 November, 2007 / TargetProcess v.2.7 Progress (program level release planning)

0 comments

We are continuing development of v.2.7. It will contain such things as program level release planning and custom reporting. Also we are re-styling user interface. You may check progress at preview.targetprocess.com (admin / admin)

Program level release planning will resolve many problems of large projects. It will provide full view on all projects releases and will allow to synchronize releases and re-plan them. Also it will show planned and forecasted product release dates.

Planning will work via drag and drop. We think that this feature will be great for product planning and high level progress tracking.

Labels: , , ,

 

We are developing TargetProcess agile project management software and blogging about our progress.

Subscribe to the RSS feed
Stay tuned by having the latest updates via RSS
Follow TargetProcess on Twitter
Get in touch with our team

Try TargetProcess
TargetProcess quick tour